ABI Binh Duong Project

ABI Binh Duong Project. Investor: AB InBev Vietnam Begin: 07/07/2014 Time to execute the work: 6 months UNICO VINA Scope:...

ABI Binh Duong Project.

Investor: AB InBev Vietnam

Begin: 07/07/2014

Time to execute the work: 6 months

UNICO VINA Scope:

  • Unloading and Install Piping and Equipment for CCT, BBT, Filtration, CIP, Yeast, Water Treatment Plan, CO2, Ammonia, Cooling and Air Compressor.
  • Install Electric Cabinet, Electric Equipment, Pulling and Connect Cable.
  • I/O Test.
  • Design, Fabrication and Installation for Main Piping Bridge.
  • Design, Fabrication and Installation for Platform in Filling Line.

—————

Pictures onsite:

  • Toolbox meeting

Perform Safety toolbox meeting every morning.

 

Weld point Sample

Sample Test: Welder must pass the Test Procedure before working onsite.

 

ABI-BBT-004-Final-BBT

BBT Area: Erection 3 BBT Tanks, Install Piping, Support and Platform

 

Utility Area

Working in Utility: Install all tanks and equipment, Air compressor,

CO2 Recovery, Cooling and Ammonia…

 

ABI-OV-006-Platform

Design, Fabrication and Installation Platform for Filling Line.

 

Piping Bridge

Main Piping Bridge: Design, fabrication and finish installation at site.

 

Piping and equipment in Filltatration

Install tanks, piping and equipment in Filtration Room, include

CIP system.

Pump in WTP

Water Treatment Plan.

ABI-CCT-007-Fina-CCT

Erection CCT, DAW tanks, install piping support and platform.

Installation was done on time according to the schedule and the factory was

opened on 21st of May,2015.