INDUSTRIAL EQUIPMENT

ABI Binh Duong Project.

Investor: AB InBev Vietnam

Begin: 07/07/2014

Time to execute the work: 6 months

UNICO VINA Scope:

  • Unloading and Install Piping and Equipment for CCT, BBT, Filtration, CIP, Yeast, Water Treatment Plan, CO2, Ammonia, Cooling and Air Compressor.
  • Install Electric Cabinet, Electric Equipment, Pulling and Connect Cable.
  • I/O Test.
  • Design, Fabrication and Installation for Main Piping Bridge.
  • Design, Fabrication and Installation for Platform in Filling Line:

Pictures onsite:

image001

3D drawing. Platform was fabrication in UNICO VINA Workshop, then made

galvanize before transport to ABi for install.

image002

Tie bolt, nut and welding to connect floor, use tube scaffolding at the high above 1.7m

image003

Install stair and handrail.

image004

Cleaning before handover.

image005

Installation done, platform ready for handover.